By Adam
Wenner and A.
Cory Lankford
On May 29, 2014, the California Independent System Operator
Corporation (CAISO) submitted to the Federal Energy Regulatory
Commission (FERC) proposed changes to its "generator downsizing"
policies. The revised policy would provide an annual
opportunity for an interconnection customer to reduce the capacity
of its generation facility by any amount and for any reason, if it
satisfies the proposed eligibility requirements and pays the
applicable restudy costs. CAISO also proposes to clarify that
an interconnection customer will not be in breach of its
interconnection agreement if it fails to develop the full capacity
of its planned generating facility, provided that the customer
downsizes its project in the next available annual downsizing window
following the scheduled commercial operation date of the generation,
as specified in the interconnection agreement.
When requesting to interconnect a generating facility to the
CAISO transmission system, a developer must specify the capacity of
its planned generation facility. CAISO will study the effects
of interconnecting the proposed generating facility to the
transmission grid, and the parties will negotiate an interconnection
agreement detailing the costs for any new facilities or upgrades
necessary to accommodate the request, and for providing
interconnection service. Developers often negotiate
interconnection agreements before they have secured contracts for
the purchase of power to be generated by their planned generating
facility. Developers that are unable to secure contracts for
all of the proposed project capacity might determine that it is no
longer economical for them to develop the full capacity of the
proposed project. Instead, they may choose to downsize the
project capacity and develop a smaller version of the project.
CAISO's existing procedures for interconnecting new generating
facilities include several options for developers to reduce the
capacity of their projects, but these downsizing opportunities are
subject to limitations. Under the CAISO's current downsizing
policy, there are eligibility requirements for developers wishing to
downsize, time limits on when a developer can exercise its
downsizing rights, and other limits on the size of and acceptable
reasons for a proposed downsizing. As a result, CAISO's
existing downsizing opportunities are not available to all
interconnection customers, or for any desired amount of reduced
generation capacity.
In response to numerous requests from interconnection customers,
CAISO proposed and FERC accepted a one-time generator downsizing
opportunity that was implemented in early 2013. In its filing
with FERC, CAISO explained that the purpose of its proposal was to
facilitate the completion and commercial operation of generation
projects that would be viable but for the inability of a developer
to construct the full capacity stated in its interconnection
request. The process also offered CAISO an opportunity to
reduce non-viable megawatts from its interconnection queue, thereby
facilitating more efficient interconnection planning. The
one-time downsizing opportunity resulted in a reduction of nearly
4,000 megawatts in CAISO's interconnection queue. CAISO
indicated to FERC that it would consider future downsizing
opportunities through its stakeholder process.
Like the one-time downsizing window implemented in 2013, CAISO's
proposed yearly downsizing opportunity is intended to balance the
need for interconnection customers to eliminate non-viable megawatts
from the CAISO's interconnection queue while protecting
non-downsizing interconnection customers from any downsizing-related
harm. In order to be eligible to participate in a yearly
downsizing process, an interconnection customer must demonstrate
that it has a generating facility that either (1) has not achieved
the commercial operation date specified in its interconnection
agreement, or (2) has achieved commercial operation, but with a
total capacity that is lower than the planned amount specified in
the interconnection agreement. If the latter, the
interconnection customer's opportunity to downsize will be limited
to the next downsizing window that closes on a date following the
commercial operation date specified in the interconnection
agreement. The interconnection customer also must demonstrate
that it is in good standing with respect to the requirements of the
CAISO Tariff and the terms of its interconnection agreement.
CAISO proposes a 30-day window that will open on October 15 and
close on November 15 of each year, during which eligible
interconnection customers can submit a generator downsizing
request. The first downsizing window would open on October 15,
2014. Interconnection customers that request downsizing will
be required to pay a $60,000 deposit to be used by CAISO, and
participating transmission owners, to pay for prudent costs incurred
in administering the downsizing process. Interconnection
customers also will be responsible for an equal share of all actual
costs in connection with studying the generator downsizing requests,
and for all costs related to amending their respective
interconnection agreements. If actual study costs incurred are
less than the generator downsizing deposit, the interconnection
customer will be refunded the balance of its deposit, with
interest.
The downsizing study will evaluate the effects of the reduced
capacity on the interconnection queue and identify any necessary
modifications to upgrades identified in the original interconnection
studies. It is expected that a reduction in capacity will
result in the identification of lower-cost upgrades, or the
elimination of upgrades altogether. However, in order to
protect interconnection customers that choose not to downsize their
generating facilities from any effects caused by downsizing
requests, CAISO proposes to continue to require downsizing customers
to finance the costs of (1) network upgrades identified in their
original interconnection studies, and (2) alternative network
upgrades identified in the downsizing study. CAISO's language
suggests that a downsizing generator will be responsible for the
costs of two alternative sets of upgrades; however, language
elsewhere in the proposed tariff revisions states that the
downsizing generator will not be responsible for any costs in excess
of its original cost responsibility as identified in its original
interconnection agreement. Even with this understanding, the
rationale for requiring the generator to be responsible for two
alternative upgrades is not clear. This topic would be
appropriate for comments seeking clarification.
CAISO also proposes to revise the existing "safe harbor"
provisions of its pro forma interconnection agreement to
offer all interconnection customers an opportunity to make de
minimis reductions in generator capacity without risking breach
of the interconnection agreements, and without participating in the
annual generator downsizing process. Currently, CAISO allows
interconnection customers to reduce the capacity of their generating
facility by up to five percent for any resource up to its commercial
operation date. CAISO proposes to expand this safe harbor by
amending its interconnection agreements to permit an interconnection
customer to reduce the capacity of its generating facility by the
greater of five percent of its capacity or ten megawatts. As
proposed, reductions of generator capacity under the expanded safe
harbor provisions must not exceed 25 percent of the capacity of the
facility.
Finally, CAISO proposes to eliminate the ability for
interconnection customers to use the CAISO's "material modification"
review process to reduce the capacity of their generating facilities
without having to submit new interconnection requests. In its
filing letter to FERC, CAISO explains that the material modification
review process is inefficient because it requires a piecemeal
evaluation of individual downsizing requests, which often involves
significant restudies of proposed interconnection requests.
CAISO also suggests that the material modification review process
will be unnecessary if interconnection customers have an annual
downsizing opportunity, as proposed to FERC.
Comments on CAISO's proposal are due by 5 PM Eastern on Thursday,
June 19.
Click here
for a copy of CAISO's FERC filing and proposed CAISO Tariff
language. For more information about this matter, please
contact:
Adam
Wenner Partner [email protected] (202)
339-8515
Cory
Lankford Managing Associate [email protected] (202)
339-8620 |